MINIMIZING DOWNTIME FOR ADVENT HEALTH NORTH PINELLAS' CEP REPLACEMENT.
PROJECT NAME.
Advent Health North Pinellas Central Energy Plant EP Project
CUSTOMER.
Advent Health North Pinellas
MARKET SECTOR.
Healthcare
SERVICES.
Design-Assist
General Contracting Services
Mechanical Contracting Services
THE CHALLENGE.
Due to the aging mechanical systems, Advent Health was in need of a complete change out of their central energy plant and all associated chillers, pumps, cooling towers, and main condensing water piping.
- The active hospital had to remain operational during the replacements
- Overall logistics of dismantling the cooling towers and chillers
THE SOLUTION.
Our team worked in tandem with Advent Health to review design alternatives, develop the right budget and schedule that met their needs for this replacement project. To minimize downtime in the active facility, our team provided several sets of taps to connect temporary chillers in various locations based on the in-depth phasing plan that was created for this project.
- Zero downtime to the chilled water system
- Overall cost & schedule goals were met
- Expediated the design to construction through the use of the design-assist delivery method
LEARN MORE ABOUT THIS PROJECT SOLUTION.
“BESIDES THE DESIGN EFFICIENCY, COST AND SCHEDULE IMPROVEMENTS EXPERIENCED BY THE PROJECT AS A RESULT OF THE PROJECT DELIVERY, THE REAL WINNER WAS ADVENT HEALTH NORTH PINELLAS IN THE DISCOVERY OF A MAINTENANCE AND SMALL PARTNER PROJECT.”
DOUG ARMSTRONG
Advent Health North Pinellas