MOFFITT CENTRAL ENERGY PLANT UPGRADE.

PROJECT NAME.

Moffitt Cancer Center – Central Energy Plant Infrastructure Upgrade & Replacement

CUSTOMER.

Moffitt Cancer Center / Gilbane Building Company

MARKET SECTOR.

Healthcare

SERVICES.

Design-Assist

Engineering Peer Review

Virtual Design & Construction (BIM Coordination)

Pre-fabrication

CEP Mechanical, Plumbing, Sheetmetal Construction

Commissioning Assistance

Service & Maintenance

THE CHALLENGE.

Harper was challenged with building the new mechanical and plumbing systems for this new central energy plant.

  • Scheduling (speed to market)
  • System Coordination
  • CEP System Turnover and Service Provision Prior to Expansion Completion
  • System Maintenance Until Substantial Completion
  • Extended Warranty Management

THE SOLUTION.

To meet the tight schedule deadlines, Harper prefabricated 80% of the systems necessary for this project off-site in our controlled fabrication shop to reduce the safety risk and provide the opportunity to prep the site while the new systems were being fabricated.

  • In-depth BIM Coordination and Management Effort
  • System Design and Layout review
  • In-depth Assistance in Commissioning and Turn-over
  • Maintenance Package provided through Substantial Completion Effort
  • Extended Warranties provided by Equipment Vendors and Harper